Touchdown Memorial Home for Horses is investing in a new Indoor Arena.

You will find the time line below of planning permissions, building standard approvals and Covid-19 in between.

You will find the latest updates on this page of this large project.

November 2020

No more stopping now, we have building standards permission so our indoor area is all go and will be constructed at Robinsons for delivery in February 2021.

Our regular contractor McLaren will work on the foundations beforehand.

August 2020

Finally the digger was allowed on site to dig the extra 4 test holes for our building standards, one of them was about 3 meters deep until the hard core.

April 2020

The planning permission for our Indoor Arena has been approved, however we have to dig some extra holes for the Building Standards. Due to Covid-19 we are unable to hire a digger so we have to wait until the lockdown lifts.

2017

Back in 2017 the idea of an Indoor Arena back started to finalise and our architect designed the indoor arena, and approved by our board of trustees

Café – Indoor arena

The café is part of this project so you can enjoy a refreshment with some homemade bakes and view the activities in the indoor area.

This space will be used for our social activities e.g. Countrymen’s club so that the gentleman can enjoy the indoors with coffee after having their outside activities.